Employer :WASCO ENGINEERING LTD
Position : Planning Lead
Project Title : PAPA-TERRA Field Development PETROBRAS - FPSO Skid Package
Based : Singapore
Project Valued : USD148 Million
Project Phase Worked: Define/Execute
Accomplished:
• Established baseline schedule Define & Execute Phase to level 5 Schedule / Weightages quantification to support progress payment on value earned by man hours
Complexity:
• Assigning task monitor log in Primavera for respective stake folders deliverable accountability - This help the project manager to monitor deliverable Progress and man hours spend