Good afternoon all,
I'm trying to pull together an engineering specfic layout with EV info and have hit a stumbling block with filtering.
What I am trying to do is only show activities with a certain set of resources assigned, plus filter to only show the hours for these resources. e.g. a management activity with 50 hrs for lead eng and 50 hrs for planner, filtered would only show the 50 hrs for lead eng. Is this filter possible?
I tried from a different angle and tried to get something similar from the Resource Assignment View, which at first seemed to meet all requirements except info on CPI/SPI. Is it possible to show EV data at this level?
Thanks