Hi All, I hope someone would be able to help me out ASAP!! :)
I fished building this Schedule and now that its time to export the curves into excel i'm having difficulties.
Keep in mind that aproximately 50% of this plan is critical and the complete plan is purely logic driven. Analising the logic one would say that the logic is sound and there aren't any problems. Also the Budgeted curve and early finish curve are literally identical. No actuals...
The budgeted curves is the basic Cum Budgeted Units, Early finish and late start curves. Normally the Early finish will finish before your Budgeted curve and in my case this early finish curve is finishing after my Baseline and before my late start...??
What is causing this strange catastrophe?