When using a resouce curves to assign cost to the very end of an eactivtiy, the cost is not always in the correct month if end of the activity is in the first few days of the month,
I assume that when creating a curve it doesnt actually have it as 100% at the end rather between 95%-100% hence the cost not appearing in the right month.
Can anyone explain a way of having the budgeted costs on the very last day of activity in resource assignemnt view?
Thanks