Hi,
Is there a way to automatically level resources if I have more that one resource assigned to an activity? Say I have an activity 100 days long and the second resource assigned is only 10 days long. By default P6 makes this second resource start at the beginning of the activity. This does not change when I resource level. Ideally I would like this 10 day resource to move around within the 100 day activity until it finds its optimum start/finish dates within the 100 days to allow for more compact resource leveling with other similar resources in different activities. I can change the dates manually to get what I want but for +500 activities this is not really practical. Any thoughts? Cheers, ool.