Hey all,
I am concerned about pausing an activity and how?
Currently my problem is ,I had scheduled an activity B to start after A , but due to certain site conditions A won't start and B will start as planned. But since A is having FS relationship with B, the schedule will show a delay and show unrealistic dates . Can any one explain what can be done