Hi,
After importing a time schedule to a BIM tool (such as Navisworks or Synchro) to produce a 4D BIM project, :
a) do you perform all the time schedule updates (follow-up) in the BIM tool exclusively? or
b) do you perform all the time schedule updates (follow-up) in the time schedule tool (Microsoft Project or Oracle Primavera) and afterwards you import again the time schedule to the BIM tool (2 steps update)?
All your opinions or experience are welcome.
Thanks