Dear Experts,
We have a program fully loaded with cost and manpower. The problem that we are facing right now is that lots of costs that were loaded to the program are not spreading to the entire duration of the activity.
Can anyone share his knowledge on resolving this issue?
Thanks in advance.
Celso