Dear All,
I have imported a schedule from P3 to P6, all seem to be working fine untill I tried to update actuals.
the schedule early finish and early end dates seem the same. no effect on succesor activies .
how can i over come this problem
Dear All,
I have imported a schedule from P3 to P6, all seem to be working fine untill I tried to update actuals.
the schedule early finish and early end dates seem the same. no effect on succesor activies .
how can i over come this problem