The contractor has several activities that are tied to its successor with both an fs and ff ties. Activity 1 – 7/08/13 – 7/10/13 Activity 2 - 7/10/13 – 7/12/13. No lags on either relationship. Would this cause the activity to act like it has a fs-1 relationship?