I have two activities in my P6 schedule that have a star next to the start date but when you look at the activity details under the status tab, it shows no constraint. I scheduled and the star remains to be there. Any ideas of how to fix this?
I have two activities in my P6 schedule that have a star next to the start date but when you look at the activity details under the status tab, it shows no constraint. I scheduled and the star remains to be there. Any ideas of how to fix this?