I am relatively new to NEC and am working on a large project.
My main question is how should equipment be paid? The contract allows for CECA (-15%)
Issues like night shifts (full shifts or not), working days (full days or not) and standing time (disallowed?) are proving to be points of conflict.
Any advice/comments would be most helpful.
Regards
Paul Russell