Hello All,
Is it possible to get an hour by hour resource distribuition in P6 ? I have prepared a shutdown programme which is resourced at an activity level but when I switch to activity / resource usage profile it seems to accumulate effort / unit on very first hour of the day against spreading it along a 24 hr work period in accordance with task sequence
Any help would be highly appreciated
Thanks in advance