Hi,
I am adding logic and removing restrictions to a schedule originally made in MSP. I got only a PDF with predecessors and activity dates and it is obvious that most dates are based on activity restrictions. However, it is also obvious that many of these restrictions can be replaced by links. I startet replacing restrictions with links, however, I lost track of how many restrictions I have removed and how many links I have added. I must list the differences between the MSP schedule and the Spider Schedule, as the schedule I am preparing will be used as baseline for an EOT claim.
Is it possible to get a report of the changes in logic between 2 versions of the same schedule?
Saludos,
Carlos.