Hello All,
I have Prepared a schedule in P6 and after making initial schedule and Assigning cost to all activities (No Resource Loading Required for the project,only activity cost from BOQ),I saved the Schedule as Primry Baseline.Now When I update the Schedule the Bars before and after the Data date Line are broken.
This Problem is not occuring in Duration % Complete type.Can anyone tell me the reason?