Guys,
Extra hands please!
I have used 2 calendars, 10hrs(7am-6pm, 1hr break) and 8hrs(8am-5pm,1hr break) in my schedule. 10hrs calendar is assigned to construction activities while 8hrs calendar is for consultant/client related activities. When I linked the construction activity to consultant activity, it is starting at 5pm,same day as predecessor finish-FS relationship. This in fact & I believe should be starting at 7am,next day because it is using 10hrs calendar and also I have changed in the SCHEDULE, OPTIONS to use Successor Activity Calendar..Please advise on how to correct it.
Thanks
Ariel