Hello all,
any help would be greatly appreciated,
I have an activity on a 12 hour calendar, the Budgetted Labor Units on the activity is 1433 hours, with a Duration (days) of 30, the remaining Labor Units (on the Status Tab) reads 1433 as the activity is at 0%.
My question is this,,, why on the Resources Tab does the Remaining Units read 1745 and NOT 1433??
many thanks