The pros and definitely the cons are clear as to use data on summary tasks in schedules. No relationships, resources and so on. But is there anybody out there that could advise me as to use risks on summary tasks, while using Oracle Primavera Risk Analysis (Pertmaster), or not to. There our different opinions within my company with regard to the assignment of risks to summary tasks. All input is greatly appreciated.
For instance; I have Phase A regarding activities 1-5. I have a 10% existence risk with a duration of 10 days. Do I link the risk to my summary? Or divide it on to my activities at say 2 days apiece?