To everyone please,
I’m new in primavera. I just want to ask why is it that when I execute Update Progress in P6 the Actual Progress Duration will go back to each Original Duration, same as Baseline, even if the Actual Progress Duration is different from Baseline …Are there steps I miss?
Note that: I have already loaded it with resources and created already a baseline. Can anyone help me?
Thanks,
Nanz