Does anyone know the size (duration and cost) of the default project for which the cost and schedule rankings were developed?
The idea is to be able to adjust the current rankings to fit a specific project. Currently the rankings are:
VH 40-> days, $600K - >
H 20-40 days, $150-600K
M 10-20 days, $75-150K
L 5-10 days, $30-75K
VL 0-5 days, 0-30K
N 0 days, $0
Any thoughts appreciated. The project against which I wish to make the assignments is worth about $800K and takes about 9 months.