I am confusing with man-months notation. I have to prepare a schedule for bidding and I have been given man-months of 10,155 (Man-Months), So man hours will be calculated as 10,155x30x10 (Man-Months x Month x Hours)?
Is it true as i got confused.
Thanks
I am confusing with man-months notation. I have to prepare a schedule for bidding and I have been given man-months of 10,155 (Man-Months), So man hours will be calculated as 10,155x30x10 (Man-Months x Month x Hours)?
Is it true as i got confused.