Hi All!
I am having troubles with the dates on my new baseline. I have updated my current project and I wanted this as my new baseline. When I assign my current project as my new baseline, the dates on Baseline start and Baseline finish columns are different from the actuals. Please can anybody help me with this?
I am having troubles with the dates on my new baseline. I have updated my current project and I wanted this as my new baseline. When I assign my current project as my new baseline, the dates on Baseline start and Baseline finish columns are different from the actuals. Please can anybody help me with this?