Can anybody know how to set baseline after we revised the Schedule and to set this revised Schedule as a baseline to the revised current schedule.??
When I tried by Project - Maintain baselines- add- save a copy of the revised schedule and assigned to the revised current schedule, it gave me wrong baseline dates and all completed activities having without Actual dates in it.
Please help,
Best regards,
Abbas