Dear Planners,
The following crane time study for typical lifting operations is for sharing. Pls comment if any other suggestions or additional information.
(Assumptions: High rise building with 90m height, tower crane model is Liebherr 200)
1. Precast element installation 8 mins/unit
2. System wallform installation 8 mins/unit
3. Remove wallform 5 mins/unit
4. Wall concreting 5 mins/cum
5. Slab & beam concreting 4 mins/cum
Regards,
KS