Does anyone know how Pertmaster treats Level of Effort activities when determining cost?
If an indirect cost (supervision, support staff, equipt. rental, etc.) is a LOE activity with assigned costs, will those costs move with the underlying (driving) activities?
Should LOE activities be ranged (max, min) or do the driving activities provide the ranging?
If not, how is the best way to handle indirect costs?
Any thoughts appreciated. Thanks.
If an indirect cost (supervision, support staff, equipt. rental, etc.) is a LOE activity with assigned costs, will those costs move with the underlying (driving) activities?
Should LOE activities be ranged (max, min) or do the driving activities provide the ranging?
If not, how is the best way to handle indirect costs?
Any thoughts appreciated. Thanks.