Hi All True Planners
The only true critical path is developed by a FS link between activities - all other adaptations are wrong.
Lazy - Inexperienced - Ignorant Planners will disagree - Bring it on now - I am waiting. (you too Charleston)
This is the code according to MT.
Every activity should represent 1 trade in 1 location anything longer than 10 days is too long.
Use bottom up planning to form programme levels:
1. Task
2. Task summary
3. Zone / Section
4. Project
Never ever use:
Lead Lag Links + or -
SS and/or FF Links
Mid Chart Links
Start - Stop Constraint flags.
ALAP positioning.
A Task with no outgoing link.
All of the above combine to distort the true critical path.
Why do the software suppliers still allow these abominations in their systems.
True planners everywhere - join me in my crusade to ban these abominations.
Best regards
Mike Testro.
The only true critical path is developed by a FS link between activities - all other adaptations are wrong.
Lazy - Inexperienced - Ignorant Planners will disagree - Bring it on now - I am waiting. (you too Charleston)
This is the code according to MT.
Every activity should represent 1 trade in 1 location anything longer than 10 days is too long.
Use bottom up planning to form programme levels:
1. Task
2. Task summary
3. Zone / Section
4. Project
Never ever use:
Lead Lag Links + or -
SS and/or FF Links
Mid Chart Links
Start - Stop Constraint flags.
ALAP positioning.
A Task with no outgoing link.
All of the above combine to distort the true critical path.
Why do the software suppliers still allow these abominations in their systems.
True planners everywhere - join me in my crusade to ban these abominations.
Best regards
Mike Testro.