Guys,
Sometimes when I import progress into P3 say in the order below;
Activity Id Percentage Actual Start ActualFinish
AB1000 100% 23/07/08 23/07/08
P3 stores the Actual start and finish dates in the order below;
Actual Start Actual Finish
23JUL08 00:00A 22JUL08 23:59A
Hence making the actual duration 0; has anyone faced this challenge before? Please share how you dealt with it... Thanks...
Sometimes when I import progress into P3 say in the order below;
Activity Id Percentage Actual Start ActualFinish
AB1000 100% 23/07/08 23/07/08
P3 stores the Actual start and finish dates in the order below;
Actual Start Actual Finish
23JUL08 00:00A 22JUL08 23:59A
Hence making the actual duration 0; has anyone faced this challenge before? Please share how you dealt with it... Thanks...