I have imported a program from P3 to P6 (Baseline & Actual) , and i got everything, targets, actual dates, progress etc,.
However, in P6 the the subtotal of "Schedule % Complete is not showing correctly, it doesnt show any thing it remains 0%, but for individual activities it is showing correctly as exactly in P3
and For "Duration % Complete", there is a subtotal but not tallying with the values on P3, but for individual activities it is showing correctly.