I have come across a problem today when re-baselining one of my plans, after re-baseling,activities that are in progress and have a remaining duration
example - 60% complete to time now
40% remaining
what is happening is that there are 256hrs remaining to end completion date 3months from time now, the baseline has calculated that 40/100x256/3months this is only given me approx 50% of the remaining resource hours and makes my forecast all out of sink
if someone has come across this, please help (-:
all my baseline data up to timenow is perfect
regards
Susan
example - 60% complete to time now
40% remaining
what is happening is that there are 256hrs remaining to end completion date 3months from time now, the baseline has calculated that 40/100x256/3months this is only given me approx 50% of the remaining resource hours and makes my forecast all out of sink
if someone has come across this, please help (-:
all my baseline data up to timenow is perfect
regards
Susan