Dear Gordon,
Thanks for your responce, Ive updated resources and unit % complete is calculated aoutomaticaly but my problem is the budgeted unit which is assigned to activities that has not got actual yet, budgeted units move after data date.
I think budgeted units in current plan which is updated with new data date should be quite equal to budgeted unit in baseline.
I work with P3e-5.
Thanks.
Thanks for your responce, Ive updated resources and unit % complete is calculated aoutomaticaly but my problem is the budgeted unit which is assigned to activities that has not got actual yet, budgeted units move after data date.
I think budgeted units in current plan which is updated with new data date should be quite equal to budgeted unit in baseline.
I work with P3e-5.
Thanks.