We are using EPM 2007 for a set of very large projects. Many tasks have multiple resources working them with varying amounts of work. When these folks are statusing through PWA (my tasks) the percent complete they see and the percent complete overall for the task cannot (by us) be logically deduced. Has anyone experienced this or can you tell me what the algorithm is to calculate % complete when multiple resources are assigned. Thanks. Doug