hello great planners,
have a program for 7 buildings. works started e few months ago. as per latest update, we have an overall delay of 60 days. only 2 buildings caused the slippage as per individual completion milestones (-60 total floats each), the rest with + floats to final handover. we are now required a recovery program to the delay.
as a beginner, i am at loss as to where to make the necessary recovery.although the remaining 5 bldgs have +floats, activities for them are still delayed. do i also have to make adjustments on them?
thanks in advance
have a program for 7 buildings. works started e few months ago. as per latest update, we have an overall delay of 60 days. only 2 buildings caused the slippage as per individual completion milestones (-60 total floats each), the rest with + floats to final handover. we are now required a recovery program to the delay.
as a beginner, i am at loss as to where to make the necessary recovery.although the remaining 5 bldgs have +floats, activities for them are still delayed. do i also have to make adjustments on them?
thanks in advance