Hi
Anyone have any idea how to get the Acutals Labour Unit without apply actuals. I set up my project with % Complete type as Duration and i do not "Apply Actuals". But i want to look at the actual labour units when the job finish. Is there any idea ???
Another problem i face is, When i schedule the job every day, those job which are Not Started accordingly (BL Start) eg: BL Start date is 17-09-07
Data Date is 18-09-07 . When schedule this job on 18.09.07 all job which were suppose to start on 17-09.07 and if not started, all those activities will be jump to 18.09.07. I dont want that. I hope if i apply actuals the planned date will remain same. Isnt it ?
Is there any idea ???
Regards
Suresh
Anyone have any idea how to get the Acutals Labour Unit without apply actuals. I set up my project with % Complete type as Duration and i do not "Apply Actuals". But i want to look at the actual labour units when the job finish. Is there any idea ???
Another problem i face is, When i schedule the job every day, those job which are Not Started accordingly (BL Start) eg: BL Start date is 17-09-07
Data Date is 18-09-07 . When schedule this job on 18.09.07 all job which were suppose to start on 17-09.07 and if not started, all those activities will be jump to 18.09.07. I dont want that. I hope if i apply actuals the planned date will remain same. Isnt it ?
Is there any idea ???
Regards
Suresh