1.BOQ is missing items but shown on Contract drawings. In this situation a variation order is required or not?
2.Contract drawings missings for certain works to be done but covered in BOQ. In this situation a variation order is required or not?
Conditions of Contract - FIDIC 4
Method of measurement - CESMM3
Thanks