have got integrated programme in excess of 10000 activities, spanning three major partners A,B,C, during checking after the independent update by partner (B), the resources got doubled when i did the checkin as the main partner(A) thus the total budgeted cost doubled,
hope such simillar incidents have given us some food for thought,
your valued advices/ experience to solve such erros is solicited
Waseem Saber