Hello all,
This is regarding preparation of Summarised Progress report of project schedule.
In a project schedule,let us consider an operation,which consists of some 5 activities.out of that, 3 activies are the main works,90% complete[we say as completed substantially].And other 2 activities,which is say,final cleaning up works,which is 0% complete.
So,when u summarise the operation it will take an average of 55%.This makes an embarassing report about that operation.
Can anyone say whether the less important works can be prioritised or ranked or given weightage ,which prevents reporting like this.
with thanks & Regards
CS.Kumar
This is regarding preparation of Summarised Progress report of project schedule.
In a project schedule,let us consider an operation,which consists of some 5 activities.out of that, 3 activies are the main works,90% complete[we say as completed substantially].And other 2 activities,which is say,final cleaning up works,which is 0% complete.
So,when u summarise the operation it will take an average of 55%.This makes an embarassing report about that operation.
Can anyone say whether the less important works can be prioritised or ranked or given weightage ,which prevents reporting like this.
with thanks & Regards
CS.Kumar