hi..
This coming September marks the 2nd year of my profesion as the scheduler in oil/gas industry.
i understand to calculate the weightage but i dont know how to determine the daily planned value % vs the actual value % to develop s-curve. For the time being , all my projects are lump sums basis and using manhours as my budget qtty. I usually reporting to the sr. planner on daily project progress using P3 Software.
Appreciate if somebody can give me clues how to calculate for the above.
Thanks!
This coming September marks the 2nd year of my profesion as the scheduler in oil/gas industry.
i understand to calculate the weightage but i dont know how to determine the daily planned value % vs the actual value % to develop s-curve. For the time being , all my projects are lump sums basis and using manhours as my budget qtty. I usually reporting to the sr. planner on daily project progress using P3 Software.