Hi All you gr8 Planners,
Im new to planning and i have this project Which is an high rise tower or 310mtrs. I want to calculate Manhours for this project which is of 32months.I can load into p3 our budgeted manhours as per trade wise(mason,steelfixers,carptrs etc.)
Guys I would like to know other way of caulating Planned Hours ...and providing s-curve for same ?
U have any productivity rates for each works and U calculate according to that?