I would like to know, when resources are loaded into the activites there are limitation where we cannot load or may be donot include all the equipments practically used in the exceution of the activity and rather prefer to load the major resources involved; normally due to increased activity count and the time constraint......
1. How can we expect to start up costing on the activities when all the equipments are not included.
The cost of the minor equipments will thus not be included and thus gives us a value lower than the actual cost!
2. On plant & labour projections generated from P3., when actuals from the site varies we have to change the values generated from p3 for reporting purposes although this depends on the efficiency of the plant involved too and sometimes the unexpected circumstances in the sites result in variation in manpower utilizatiton.
i.e. in short we just get a rough idea from projections.
Is this all that we can expect from projections or am i far away from the real idea involved...:-?
........................Cheers..............all........
1. How can we expect to start up costing on the activities when all the equipments are not included.
The cost of the minor equipments will thus not be included and thus gives us a value lower than the actual cost!
2. On plant & labour projections generated from P3., when actuals from the site varies we have to change the values generated from p3 for reporting purposes although this depends on the efficiency of the plant involved too and sometimes the unexpected circumstances in the sites result in variation in manpower utilizatiton.
i.e. in short we just get a rough idea from projections.
Is this all that we can expect from projections or am i far away from the real idea involved...:-?
........................Cheers..............all........