Hello all Planning Planet friends!
Do you have any experience with setting up an multiproject in OPE? I have many OPE project, which I have to "put together" to multiproject file. Each of them has correctly set up start and finish date in project dates, but when i insert them into one file as external subproject and I run the time analysis with date now set to the oldest start date from all subproject all projects start dates changes to this date. Can you help me? How is it possible to solve this issue?
Thank you for your help.
Do you have any experience with setting up an multiproject in OPE? I have many OPE project, which I have to "put together" to multiproject file. Each of them has correctly set up start and finish date in project dates, but when i insert them into one file as external subproject and I run the time analysis with date now set to the oldest start date from all subproject all projects start dates changes to this date. Can you help me? How is it possible to solve this issue?