Ive seen the threads and postings regarding BCWS not calculating at the summary level but my Project (2000 SR-1) randomly does not calculate BCWS data at the task level.
The majority of the tasks have BCWS calculations but many do not and as a result my overall BCWS is always zero...
Ive tried rebaselining but it doesnt seem to help at the task level.
Anyone know a workaround?
Thanks!
The majority of the tasks have BCWS calculations but many do not and as a result my overall BCWS is always zero...
Ive tried rebaselining but it doesnt seem to help at the task level.
Anyone know a workaround?
Thanks!