Dear experts,
I have two schedules of a same project. One is the original baseline and the other is the revised. some of the activties from the original schedule have been deleted in the revised schedule.When we set the original baseline as primary baseline to the revised schedule,baseline budget figure only reflects the figures related to the activties in the revised schedule but not the total budget in the primary baseline.Is there any option in P3e to show the total budget when set as the primary baseline.
Sorry if it is a silly question (I am new to P3e)
Your kind advice will be highly appreciated.
Thanks & regards
Dinesh