Which relationship like FS or FF (with positive lag) is the best practical way to use in order to form a critical path? in my opinion all activities must have finish to start relationship if we have enough detailed break down. During the absence of such details(delay in awarding sub-contract works)what could be done? i leave this question to our fellow planners.....................
What is the easiet way to group multiple critical paths in P3. Other than Navigating through driving relationships and assign some custom codings corresponding to each critical paths..............