schedule % complete

1 reply [Last post]
Anil M G
User offline. Last seen 6 years 32 weeks ago. Offline
Joined: 15 Aug 2017
Posts: 2
Groups: None

Hi ,

I have some issues,

I need to use Expense Cost and Man-hour related progress. I want to see the Planned progress and Actual progress based on the Expense Cost and Man-hour same time.

I believe we can load Expense Cost as well as Man-hours to the Schedule.

Now the issue how to get Schedule %? How to get Schedule% based on Expense Cost and based on Man-hours separately.

Is it possible?, How it can be switched in P6?

Replies

Zoltan Palffy
User offline. Last seen 3 days 1 hour ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

view show on bottom resource useage profile