% Complete Column

3 replies [Last post]
Andy Hudson
User offline. Last seen 6 years 30 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Hi,

Please see attached screeenshot (http://ge.tt/7uuG97m2 ). . I previously used it in Asta.

Now I need your help to do so in P6:   

a) How to give Weekly planned % complete column and actual Weekly  % Complete column as I highlighled in rectangle?

b)How to show different weekly progress lines on bar chart at the same time as highlighted in screenshot?

Please advise.

Cheers

Andy

Replies

Andy Hudson
User offline. Last seen 6 years 30 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Thanks Zoltan and Dave

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

for planned you have to have a baseline attached 

David Kelly
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Andy,

 

P6 only roles up, indeed only stores % to date for current and baseline schedules. 

A spreadsheet view of quantities forecast per week is simple, but expressing those as percentages is barely possible, making those percentages roll up is impossible.