Issues in calculate the projects completion%

2 replies [Last post]
Abdulaziz Bin Emran
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 5 Apr 2017
Posts: 2
Groups: None

Hi 

 

For example, 

Project A have 2 Milestones start in 2017 and 2018

The work in milestone 1 is 100% complete , which is represent the major efoort og the whole project 

milestone 2 is actually to do FQA 

the point is the system we have consider all milestones as one weight which is not represent the reality.

 

* I can not use weghts formula because of top management order !

I need to came up with another soluation.

Replies

urvashi tyagi
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 10 May 2017
Posts: 2
Groups: None

Hi Emran,

Check out PineStem(PineStem.com) Project management tool, it might be helpful for you. Here are the main features to contribute to your project success or to check the status of your project:-

1.Project planning :- Through user stories, tasks, sprint creation, sprint burndown chart, you can monitor the progress of your project and can do the proper planning of it.

2.Project status-To check the current status of the project,this tool use different reports such as Employee load graph,project load graph, which shows the current load of any employee across project and your project status too in terms of tasks load and it's status.

As i said there are different reports which suits your needs, few of them are:-

Sprint comparison report- which show the comparison of the sprint in a project and it's progress in terms of total budgeted hours, total spent hours, total number of tasks and bugs created in each sprint.Hence help you in motinoring your project progess throuhg sprints.

And  many more new reports are coming soon thereby keeping you on the top of the analysis of your project . And also helps you to moitor your project performance .

Zoltan Palffy
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

milestone 1 50% milestone 2 50%