Calculate activities

No replies
Alexandre Faulx-B...
User offline. Last seen 1 day 40 min ago. Offline
Joined: 20 Jan 2003
Posts: 1200

Hello Planners,

I am trying to calculate an activity duration as: Quantity/Planned work rate value; I would like to obtain an integer figure for the duration instead of a fractionary, for example: 25000/10000= 2 and not 2.5

is it possible?

Thank you for your help

Alexandre