Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Construction Sequence of Subsea Tunnel.

4 replies [Last post]
xadlim B.
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 4 Feb 2012
Posts: 25

Hi Guys,

Anybody could enlighten the general steps in construction sequence of Subsea Tunnel particularly Cut & Cover and TBM methods?

 

Thanks and regards,

Replies

xadlim B.
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 4 Feb 2012
Posts: 25

Thanks Mike, it gives me further ideas.

Mike Testro
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Xadlim

The Tunnell Boring Method depends on two main factors:

1. Subsea conditions - it has to be impermeable.

2. Length of tunnel - it has to be long enough to be worth the deployment of a bespoke tunnel head.

Considering the English Channel tunnel it was bored through stiff clay and the 22 mile length allowed the economical deployment of two machines.

Best regards

Mike Testro

xadlim B.
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 4 Feb 2012
Posts: 25

Thanks for your valuable respond Mike.

Any great thoughts with the TBM method guys?

 

K/R

Mike Testro
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Xadlim

I recall the cross harbour tunnel that was built across the harbour in Hong Kong which was a cut and cover operation.

It was in relatively shallow water and was not too long which allowed the process.

A trench was dreged across the harbour and precast concrete boxes were lowered into the trench. The boxes were linked with tension cables. The joints between the boxes were gouted and the cables stressed to seal the entire tunnel. The trench was re filled to the original sea bed level and the water was pumped out.

You cannot do this in sections - it has to be the entire tunnel.

I hope that helps

Best regards

Mike Testro