Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline and Layers

1 reply [Last post]
Alexandre Faulx-B...
User offline. Last seen 1 year 47 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355

Hello PPers,

Is it possible to assign two different layers to the current task and its baseline?

Thank you

Replies

Thorsten Balthasar
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 14 Jun 2011
Posts: 15
Groups: TILOS

Alexandre,

No, task and baseline has the same layer, but:
if you want to switch off the visibility of selected baseline tasks you may use the "Visible" flag in the baseline manager.

regards

Thorsten