Baseline and Layers

1 reply [Last post]
Alexandre Faulx-B...
User offline. Last seen 1 day 5 hours ago. Offline
Joined: 20 Jan 2003
Posts: 1254

Hello PPers,

Is it possible to assign two different layers to the current task and its baseline?

Thank you

Replies

Thorsten Balthasar
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 14 Jun 2011
Posts: 15
Groups: TILOS

Alexandre,

No, task and baseline has the same layer, but:
if you want to switch off the visibility of selected baseline tasks you may use the "Visible" flag in the baseline manager.

regards

Thorsten