100% of the cost at the beginning of the task

1 reply [Last post]
Alexandre Faulx-B...
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355

Hello,

I need to allocate a lump sum cost to some tasks of the project, and have 100 percent of the cost showing at the very beginning of the task. Can anybody help?

Alexandre

Replies

Thorsten Balthasar
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 14 Jun 2011
Posts: 15
Groups: TILOS

Alexandre,

 

by default TILOS spreads the cost allocation on the duration of the task.

For your need you may
- create a milestone for each of the corresponding tasks
- assign Start-Start-Links to locate the Milesones at the beginning of the task

- assign the cost to the milestone
- you may also switch off the display of those milestones with layers or filter

 

regards

Thorsten